New Scotland Yard

Project Description

A two phase project was completed at New Scotland Yard by Airtemp for Mace.  The first phase consisted of providing cooling to the power supply room for the critical server room. Using Daikin floor mounted cooling units on a duty rotate, lead lag setup the system was successfully installed and commissioned and integrated into the Trend BMS system.

Phase 2 involved new Daikin twin & single split systems being supplied and installed throughout the 8th floor office area. This helped control the temperature issues that had become problematic as the building had evolved over the years.

The project was completed and successfully handed over in a 6 week period.

Project Details

Client / Project Name:
Mace / New Scotland Yard, Sorisso Department

Project Value:
£95,000

Design:
Design by Atkins Consulting Engineers

Programme:
6 weeks

Project Type:
Office fit out

-